The following is an update of the construction to take place for the week beginning Saturday, January 11, 2020.
Southbound I-91 bridge activities:
Monday through Friday:
- Continue girder closures
- Demolition of remaining old northbound pier footings
- Continue maintenance of traffic control devises
NOTE: The scheduled rolling road blocks are complete as all the girders have been erected.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!