The following is an update of the construction to take place for the week beginning Saturday, January 11, 2020.

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue girder closures
  • Demolition of remaining old northbound pier footings
  • Continue maintenance of traffic control devises

NOTE:  The scheduled rolling road blocks are complete as all the girders have been erected. 

NARROW LANES – REDUCED SPEEDS – USE CAUTION!