The following is an update of the construction to take place for the week beginning Tuesday, May 26, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday: No work due to the Memorial Day holiday
Tuesday through Friday:
- Work on Pier’s 1 and 2
- Bridge deck work
- Continue maintenance of traffic control devises
Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!