The following is an update of the construction to take place for the week beginning Monday, August 03, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue including installing rebar
- Continue work on the abutments to include southbound concrete placement
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
Please note the Vermont State Police will be setting up radar within the construction zone. Follow the posted speed limit.