The following is an update of the construction to take place for the week beginning Monday, August 03, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday through Friday- 6:00 a.m. to 5:00 p.m.:

  • Bridge deck work to continue including installing rebar
  • Continue work on the abutments to include southbound concrete placement
  • Maintenance of traffic control devices continues

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Please note the Vermont State Police will be setting up radar within the construction zone. Follow the posted speed limit.