The following is an update of the construction to take place for the week beginning Monday, August 24, 2020.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue
- Continue work on the abutments to include backfilling at the northbound abutment approach
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!