The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, March 25, 2019:
Monday thru Friday:
- Begin form work for Pier #3 southbound footing
- Complete install of “Sheet Pile” at Pier #2 SB for ground stabilization
- Excavation and ledge removal at Pier #2 SB cofferdam
- Continue various items for the completion of the NB Bridge to include placement of curb
- Continue maintenance of traffic control devices, due to weather