The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, May 13, 2019:
Monday thru Friday:
- Work continues on the installation of the southbound crossover.
- Work continues on SB Pier #3.
- Placement of concrete for the 1st shaft section on Pier #2.
- Begin form work for the 2nd shaft placement on Pier #2.
- Installation of the southbound traffic control devises.