Rockingham I-91

Written by on May 16, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, May 20, 2019:

Monday thru Friday:

  • Work continues on the installation of the southbound crossover to include paving, shoulders and guardrail work.
  • Work continues on SB Pier #3.
  • Continue work for the 2nd shaft placement on Pier #2.
  • Continue installation of the southbound traffic control devises. 

NARROW LANES – USE CAUTION – REDUCE SPEED!