The following is an update to the work schedule for the week beginning April 29, 2019:
Monday:
- Weather permitting, paving in Bristol at the VT-116/VT-17/Burpee Road intersection along with the surrounding area of Airport Road in preparation of final paving.
Tuesday thru Friday:
- Installation of center line rumble strip throughout the project limits.
- General cleanup work throughout the project limits.
Motorists should expect delays with traffic control present allowing for 1-lane of alternating traffic within the construction zone.