The anticipated schedule on VT 117 for the week beginning Monday, June 17, 2019

  • Weather permitting, continue installation of cold mix from Barber Farm Road to the Essex/Jericho town line.
  • Line striping throughout the project limits
  • Tentative signal installation at the VT-289 intersection  

MOTORISTS SHOULD EXPECT DELAYS!

Traffic control will be present allowing for one lane of alternating traffic.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!