The following is an update to the work schedule for the week beginning Monday, November 26, 2018:
Monday thru Friday:
- Weather permitting, continue driveway tie-ins throughout the project limits.
- Weather permitting, continued painting pavement markings to include stop bars and crosswalks.
- Placement of shoulder aggregate throughout the project limits.
- General cleanup work throughout the project limits.
Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.