ALL WORK THIS WEEK IS EXPECTED TO BE THROUGHOUT THE PROJECT LIMITS.
Monday and Tuesday:
- Continue milling the approaches on each end of the project along with all side road approaches
Wednesday through Friday:
- Driveway paving preparation work
Monday through Friday:
- Shoulder clean up and ditch work
Traffic control will be present allowing for one-lane of alternating travel within the construction zones. The speed limit will be enforced!