The anticipated work schedule for I-91 Rockingham Bridges:

Written by on July 6, 2018 in Rockingham Bridges-I91

For the week beginning Monday, July 09, 2018:

I-91 northbound bridge activities:

 Monday:

  • Dismantle one crane to relocate (this may go into Tuesday)

 Tuesday thru Friday:

  • Complete beam erection with daily rolling road blocks see below
  • Truck traffic on Golden Hill Road

  I-91 APPROX. ROLLING ROAD BLOCK SCHEDULES for beam deliveries:

  • Southbound: . 7:30am & 12:00pm for approx. 10 mins.
  • Northbound:   8:30am & 2:00pm for approx.. 20 mins.

NOTE:  If all beams are set by Thursday afternoon there will not be any rolling road blocks for Friday.

Please note rolling road block times could vary due to unforeseen circumstances.

*  The northbound rolling road blocks also includes the Exit 6 on ramp.  Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

Subscribe