The anticipated work schedule for the I-91 Rockingham Bridges

Written by on September 20, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 24 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of bridge deck form work and overhang.
  • Begin installing deck steel reinforcement.
  • Complete removal of temporary supports that held the beams and forms.
  • Remove back wall forms at the northern abutment.
  • Begin forming back wall at the southern abutment.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.

Subscribe

If you enjoyed this article, subscribe now to receive more just like it.

Subscribe via RSS Feed

Comments are closed.

Top