For the week beginning Monday, September 24 , 2018:
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:
- Continue installation of bridge deck form work and overhang.
- Begin installing deck steel reinforcement.
- Complete removal of temporary supports that held the beams and forms.
- Remove back wall forms at the northern abutment.
- Begin forming back wall at the southern abutment.
REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.
Connect