The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on August 23, 2018 in Rockingham Bridges-I91

For the week beginning Monday, August 27 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of overhang.
  • Begin installing the steel decking
  • Begin removal of temporary supports that held the beams.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.

Subscribe

If you enjoyed this article, subscribe now to receive more just like it.

Subscribe via RSS Feed

Comments are closed.

Top