For the week beginning Monday, August 27 , 2018:
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:
- Continue installation of overhang.
- Begin installing the steel decking
- Begin removal of temporary supports that held the beams.
REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.
Connect