The anticipated work schedule for the week beginning Monday, July 22, 2018 on VT 117:

Monday thru Friday:

  • Continue roadway excavation in various areas between Tiffany Lane to Sand Hill Road.
  • Begin reclaiming the roadway from the Essex/Jericho Town line proceeding north. Reclaim takes 10″ of the road surface and basically rototills it and places it back as a gravel surface, recycling the existing material.
  • ROADWAY MAINTENANCE THROUGHOUT THE PROJECT!

 Motorists please be aware that the roadway surface will be rough for a duration of time – please drive slowly!   

Roadway maintenance will be ongoing, as needed.    

Commuting motorists should seek alternate routes.  Expect delays during peak hours!