The anticipated work schedule for the week beginning Saturday, September 7, 2019

Written by on September 6, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Saturday, Monday through Friday:

  • Weather permitting, complete final paving on VT 117 to the VT Route 2 intersection in Richmond and begin paving abutting side road tie-ins.

Wednesday:

  • Installation of rumble strip 

Thursday & Friday:

  • Weather permitting, bridge joint work throughout the project.

EXPECT EXTENDED DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!