The anticipated work schedule for VT 116:

Written by on July 5, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday,  July 09, 2018: 

Monday thru Friday:

  • Continued sign installation between Bristol and Middlebury.
  • Continued culvert replacement between VT-125 intersection to Cady Road.  This culvert replacement will cause 1-way traffic controlled by a traffic signal with a 10’ wide lane restriction.