The anticipated work schedule for VT 116:

Written by on July 26, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, July 30, 2018:

Monday thru Friday:

  • Cold planning the side road approaches and various approaches on the main line between E. Middlebury and Bristol
  • Miscellaneous clean up work throughout the project.

We are awaiting notification on the culvert work that was postponed.   I will post it if this gets scheduled for next week.