The anticipated work schedule for VT Route 116

Written by on September 20, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, September 24, 2018:

Monday thru Friday:

  • Continued pepping side roads and driveway tie-ins in preparation of final paving from Bristol proceeding south to the end of the project limits in Middlebury.

Wednesday thru Saturday:

  • Weather permitting, final paving to begin south of Bristol Village to East Middlebury.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.