The following is an update to the work schedule for the week beginning May 06, 2019:
Monday thru Friday:
- Weather permitting, side roads and driveway tie-ins throughout the project limits.
- Pavement markings on abutting side roads throughout.
- Bridge joint work throughout.
- General cleanup work throughout.
Tuesday:
- Installation of center line rumble strip throughout the project limits.
Motorists should expect delays with traffic control present allowing for 1-lane of alternating traffic within the construction zone.