The anticipated work schedule on VT 116:

Written by on October 25, 2018 in Middlebury-Starksboro VT 116

The work schedule for the week beginning Saturday, October 27, 2018:

Saturday thru Friday:

  • Weather permitting, continue paving from Cobble Road, Bristol to the Bristol Village line.
  • Weather permitting, paving abutting side roads & driveway aprons beginning in East Middlebury and proceeding north.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

Subscribe

If you enjoyed this article, subscribe now to receive more just like it.

Subscribe via RSS Feed

Comments are closed.

Top