The following is an update to the work schedule for the week beginning Monday, November 12, 2018:

Monday thru Friday:

  • Weather permitting, continue final paving from approximately VT 17/116 intersection proceeding north.
  • Weather permitting, continued paving abutting side roads from approximately Bristol Notch Road proceeding north.
  • Weather permitting, continued driveway aprons from approximately Mead Lane proceeding north.
  • General cleanup work throughout the project limits.


Thursday & Friday:

  • Begin shoulder gravel throughout the project limits.


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

We ask motorists to use extreme caution while traveling through the work zone.  The safety of the workers, pedestrians and the motorists are of the utmost importance.

Subscribe

If you enjoyed this article, subscribe now to receive more just like it.

Subscribe via RSS Feed

Comments are closed.

Top