The following is an update to the work schedule for the week beginning Monday, April 08, 2019:
Monday thru Friday:
• Weather permitting, drainage work to continue between the Essex/Jericho town line and Skunk Hollow Road
• Slope repairs between Bradley Bow Road, Jericho and Rogers Lane, Richmond
Tuesday thru Friday:
• Signal work at the intersection of VT 289 and VT Route 117
Traffic control will be present allowing for one-lane of alternating travel within the construction zones. Motorists please use caution!