The anticipated work schedule on VT 117

Written by on November 21, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is an update to the work schedule for the week beginning Monday, November 26, 2018:

Monday:

  • Continued general clean-up work throughout the project limits.

Tuesday thru Friday:

  • Weather permitting, removal of the temporary lines between Tiffany Lane and the Essex/Jericho town line and repainting the lines at the correct locations along with other pavement markings.
  • Weather permitting, overlay of the line striping between the Essex/Jericho town line to the Route 2/VT 117 intersection.
  • Guardrail work between Tiffany Lane and the Essex/Jericho town line.
  • Signal work at the VT 289 off ramp.


Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.