The anticipated work schedule on VT 117 for October 1, 2019

Written by on October 1, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue paving abutting side roads and driveway tie-ins.
  • Continue shoulder work throughout the project limits
  • Weather permitting, pavement markings throughout the project limits
  • Continue sign installation
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!