Monday thru Friday:

  • Reclaiming of the roadway surface between Skunk Hollow Road and the VT Route 117/US Route 2 intersection. 
  • Roadway excavation to begin at the Essex/Jericho town line proceeding east throughout the week.
  • Signal work at the intersection of VT 289 and VT Route 117.

Monday thru Wednesday:

  • Continued Guardrail work throughout the project limits.

Motorist should expect delays!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 