Monday thru Friday:
- Reclaiming of the roadway surface between Skunk Hollow Road and the VT Route 117/US Route 2 intersection.
- Roadway excavation to begin at the Essex/Jericho town line proceeding east throughout the week.
- Signal work at the intersection of VT 289 and VT Route 117.
Monday thru Wednesday:
- Continued Guardrail work throughout the project limits.
Motorist should expect delays!
Traffic control will be present allowing for one-lane of alternating travel within the construction zones.
Connect