Monday – No work due to the Columbus Day holiday
Tuesday through Friday:
- Weather permitting, continue pavement markings from Sand Hill Road to Route 2.
- Continue mailbox adjustments
- Project cleanup work
MOTORISTS SHOULD EXPECT MINIMAL DELAYS!
Traffic control will be present allowing for one-lane of alternating travel within the construction zones. The speed limit will be enforced!
PLEASE SLOW DOWN! SAFETY FIRST!