It’s that time of the year again!
The following is an update to the work schedule for the week beginning Monday, April 01, 2019:
Monday & Tuesday:
- Traffic control sign packages to be installed
Wednesday thru Friday:
- Weather permitting, ledge removal and underdrain work to begin between the Essex/Jericho town line and Skunk Hollow Road