Saturday:
- Continue sign installation
Monday through Wednesday:
- Weather permitting, continue hand paving abutting driveway tie-ins in Essex proceeding east.
Monday & Tuesday:
- Continue signal work at the VT-289/117 intersection
Tuesday and Thursday:
- Weather permitting, continue paving abutting side roads and large driveway tie-ins.
MOTORISTS SHOULD PLAN FOR DELAYS
Traffic control will be present allowing for one-lane of alternating travel within the construction zones. The speed limit will be enforced!