Saturday:

  • Continue sign installation

Monday through Wednesday:

  • Weather permitting, continue hand paving abutting driveway tie-ins in Essex proceeding east.

Monday & Tuesday:

  • Continue signal work at the VT-289/117 intersection

Tuesday and Thursday:

  • Weather permitting, continue paving abutting side roads and large driveway tie-ins.

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!