The following in the anticipated schedule for the I-91 Rockingham Bridges

Written by on June 15, 2018 in Rockingham Bridges-I91

For the week beginning, June 18, 2018:

I-91 northbound bridge activities:

 Monday thru Friday – Daytime:

 I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

* The northbound rolling road blocks also include the Exit 6 on ramp.  Motorists may want to follow the detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.  Oversize trucks must follow their permitted route. 

  • Continued beam erection
  • Complete removing forms from Abutment 1
  • Cleanup of Abutment 1 and begin backfilling
  • Truck traffic on Golden Hill Road

 

 