The following is the anticipated schedule for the I-91 Rockingham Bridges

Written by on June 29, 2018 in Rockingham Bridges-I91

 

The schedule beginning Friday, June 29, 2018 thru Tuesday, July 3, 2018 @ noon:

I-91 northbound bridge activities:

  • Continued beam erection on Pier 1 and to Pier 2
  • Erect 16000lb crane to Abutment 1 – southbound
  • Truck traffic on Golden Hill Road

Work to resume on Monday, July 09, 2018.

I-91 APPROX. ROLLING ROAD BLOCK SCHEDULES for beam deliveries:
– Friday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.
– Saturday: Approx. 2:30am & 4:00am southbound for approx. 10 mins. and approx. 3:15am & 7:30am northbound for approx. 20mins.
– Sunday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.
– Monday: Approx. 2:30am & 4:00am southbound for approx. 10 mins. and approx. 3:15am & 7:30am northbound for approx. 20mins.
– Tuesday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.

Please note rolling road block times could vary due to unforeseen circumstances.
* The northbound rolling road blocks also includes the Exit 6 on ramp. Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.