Work on the northbound bridge for the week beginning Monday, May 28, 2018:
Monday:
- No work due to the Memorial Day Holiday!
Tuesday thru Friday – Daytime:
- Complete installation of beam support towers for Piers 1, 2 & 3
- Continued work on Abutment 1 footings & support wall
- Mobilization of large erection cranes to trestle and abutment 2
- Preparation to begin beam erection
- Truck traffic on Golden Hill Road