For the week beginning Monday, June 4, 2018:
Monday thru Friday – Daytime:
- Continued installing beam support hardware on Piers
- Continue mobilizing cranes to needed locations
- Continue receiving beams at the lay-down area
- Continued preparation to begin beam erection to begin Thursday
- Continued concrete work on Abutment 1 for support walls
- Complete backfilling at abutment 2 and construct crane pad
- Truck traffic on Golden Hill Road
Thursday – I-91 ROLLING ROAD BLOCKS to allow for beam deliveries:
- 8:00am and 11:00am southbound for approximately 30 minutes
- 10:00am and 2:00pm northbound for approximately 30 minutes
Friday – I-91 ROLLING ROAD BLOCKS to allow for beam deliveries:
- 8:00am southbound for approximately 30 minutes
- 10:00am northbound for approximately 30 minutes
Connect