The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 8, 2018 in Rockingham Bridges-I91

For the week beginning Monday, June 11, 2018:

I-91 northbound bridge activities:

Daily I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

*  The northbound rolling road blocks also includes the Exit 6 on ramp.  Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

  • Continued beam erection
  • Complete Abutment 1 support walls and remove forms
  • Truck traffic on Golden Hill Road

 