For the week beginning Monday, June 25, 2018:
I-91 northbound bridge activities:
Monday thru SUNDAY – Daytime:
I-91 ROLLING ROAD BLOCKS to allow for beam deliveries:
- 2 daily southbound for approx.. 15 minutes
- 2 daily northbound* for approx.. 30 minutes
- Please note rolling road block times could vary due to avoidance of peak traffic flow and/or due to unforeseen circumstances.
* The northbound rolling road blocks also include the Exit 6 on ramp. Motorists may want to follow the detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays. Oversize trucks must follow their permitted route.
- Continued beam erection from Abutment 2 to Pier 2
- Begin beam erection from Pier 1 to Pier 2
- Complete backfilling Abutment 1
- Truck traffic on Golden Hill Road
Connect