The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 21, 2018 in Rockingham Bridges-I91

For the week beginning Monday, June 25, 2018:

I-91 northbound bridge activities:

 Monday thru SUNDAY – Daytime:

 I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 2 daily southbound for approx.. 15 minutes
  • 2 daily northbound* for approx.. 30 minutes
  • Please note rolling road block times could vary due to avoidance of peak traffic flow and/or due to unforeseen circumstances.

 * The northbound rolling road blocks also include the Exit 6 on ramp.  Motorists may want to follow the detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.  Oversize trucks must follow their permitted route. 

  • Continued beam erection from Abutment 2 to Pier 2
  • Begin beam erection from Pier 1 to Pier 2
  • Complete backfilling Abutment 1
  • Truck traffic on Golden Hill Road