The following is the anticipated work schedule for Bridge #8:

Written by on July 5, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, July 09, 2018. 

 Monday thru Sunday:

  •  Continue preparation for placement of concrete deck.
  • Continued work on the east roadway approaches to the bridge.
  • Placement of the concrete deck for the later part of the week.

The contractor is on schedule.

 