The following is the anticipated work schedule for the VT 117 project:

The following is the anticipated work schedule for the week beginning Monday,  June 25, 2018:

 Monday thru Friday:

  • Begin installing under drain from the intersection of 289 to N. Williston Road on the east side of the roadway.
  • Thinning and trimming trees between 289 to N. Williston Road
  • Preventative roadway maintenance at the On/Off Ramps at the 289 & 117 intersections.

Commuting motorists should seek alternate routes.  Traffic will be delayed during peak hours.  Traffic control will be present allowing for one lane of alternating traffic within the construction areas.