The following is the anticipated work schedule for the week beginning Saturday, July 07, 2018:
Saturday thru Friday:
- Continue installing underdrain from N. Williston Road to the intersection of VT 289.
- Shoulder cleanup from VT 289 interchange to approx.. Tiffany Lane.
Monday thru Friday:
- Milling to begin from approx.. Tiffany Lane, Essex to Sand Hill Road with VT 289 interchange area gapped out. This work will grind down the existing roadway 4” – motorists should prepare for rough surface conditions.
Motorists should expect long delays and may want to seek alternate routes.