The following is the anticipated work schedule for the VT 117 project:

The following is the anticipated work schedule for the week beginning Saturday,  July 07, 2018:

 Saturday thru Friday:

  • Continue installing underdrain from N. Williston Road to the intersection of VT 289.
  • Shoulder cleanup from VT 289 interchange to approx.. Tiffany Lane.

 Monday thru Friday:

  • Milling to begin from approx.. Tiffany Lane, Essex to Sand Hill Road with VT 289 interchange area gapped out. This work will grind down the existing roadway 4” – motorists should prepare for rough surface conditions.

Motorists should expect long delays and may want to seek alternate routes. 