For the week beginning Saturday, September 08, 2018:

 Saturday:

  • Weather permitting & tentatively, continued installation of cold mix from the Essex/Jericho town line proceeding west to Tiffany Lane.

 Monday thru Friday:

  • Weather permitting, continued installation of cold mix from the Essex/Jericho town line proceeding west to Tiffany Lane.
  • Underdrain and slope stabilization work continues between Barber Farm Road and the US Route 2 intersection.