The following is an update to the work schedule for the week beginning Monday, August 06, 2018:

Monday thru Friday:

  • Continued culvert work between Airport Road & VT Route 125 in E. Middlebury – Traffic will be 1 lane thru this area controlled by a traffic signal.
  • Relocation and/or replacement of various mailboxes throughout the project due to the widening of the roadway – homeowners have been directly notified of this work

Wednesday:

  • Asphalt curb installation on “Stoney Hill” between So. Airport Road & Lovers Lane.

Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.