VT 116/Hinesburg Road Culvert Replacement

Written by on May 19, 2017 in ZArchives

 

The Vermont Agency of Transportation in conjunction with CCS Constructors, Inc. will begin the culvert replacement on VT Route 116/Hinesburg Road at Potash Brook.  The anticipated start date June 05, 2017 with a completion date of September 01, 2017.

This project will cause Hinesburg Road/VT Route 116 to be closed to thru traffic between Williston Road and Kennedy Drive beginning in mid to late June 2017.  Pedestrians/bicycles will still have the ability to cross the construction site via a temporary bridge.

 

 

 


VT ROUTE 116/HINESBURG ROAD IS OPEN TO THRU TRAFFIC

The following is the anticipated schedule on VT Route 116/Hinesburg Road for the week beginning November 27, 2017:

 Monday thru Friday – 7:00am to 5:00pm:

  • Landscaping work continues within the construction zone well off the road.

Motorists should not encounter delays.

 


The following is the anticipated schedule on VT Route 116/Hinesburg Road for the week beginning Monday, December 04, 2017.

Monday thru Friday – Daytime:

  • Weather permitting, landscaping work within the construction zone well off the roadway continues.

Motorists should not encounter any delays.

This will be the final update for the 2017 construction season.  There will be some tree & shrub plantings next sprint to finalize the project which should have minor impact (lane closures) on the traveling public.

 