VT 117 – August 16, 2018

Written by on August 15, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule for the day is as follows:

  • 8:30am  The 2nd reclaiming phase to continue in the eastbound lane between the Essex/Jericho town line and N. Williston Road.  This phase includes adding a stabilize agent added to the subbase. This agent takes time to cure causing a maximum of 2 hour lane restriction after installation is completed.
  • 7:00am  Continued slope stabilization work between VT-289 on-ramps and Greenfield Road.

Motorists should expect traffic control with lane closures allowing for alternating traffic.

DRIVE SLOW – DRIVE WITH CAUTION!