VT 117 – August 29, 2018

Written by on August 28, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
 
  • Installation of cold mix beginning at the Essex/Jericho town line proceeding westbound.
  • Continued underdrain work will also continue between Skunk Barber Farm Road and the Jericho/Richmond town line.
Traffic control is present allowing for one lane of alternating travel.
 
USE CAUTION – DRIVE SLOW – NO CENTER LINE!