VT 117 – July 31, 2018

The anticipated work schedule is as follows:

  • Reclaiming continues between Sand Hill Road and VT 289.
  • Slope stabilization work between Skunk Hollow Road and Barber Farm Road in Jericho.
  • Begin culvert replacement approximately 1000′ east of No. Williston Road

ROADWAY MAINTENANCE AS NEEDED!

Motorists should expect delays with traffic control present allowing for one-lane of alternating traffic.

SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!