The anticipated work schedule is as follows:
- Weather permitting, paving the entrance apron on Mall Drive.
- Continued structure rehab work between VT-289 and Tiffany Lane.
- Continued culvert work around the Jericho/Richmond town line.
- Guardrail work will continue between N. Williston Road and the Essex/Jericho town line.
- Placement of gravel to abutting driveway aprons to ease the transition onto VT 117 until the aprons get paved.
Traffic control will be present allowing for one lane of alternating traffic through the work zones. Motorists expect delays!