The anticipated work schedule is as follows:
- Shoulder / ditch work will continue between No. Williston Road and Greenfield Road.
- Continued culvert work to continue between Barber Farm Road and the Jericho/Richmond town line.
- Structure rehabilitation work to continue between VT 289 ramps.
Traffic control will be present allowing for one lane of alternating traffic through the work zones. Motorists expect delays!
Motorists be aware on Thursday, October 18, 2018, weather permitting, expect paving at the Sand Hill Road intersection.
DRIVE SLOW – USE CAUTION!