VT 117 – October 23, 2018

Written by on October 22, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Pot hole patching between Barber Farm Road and the Jericho/Richmond town line.
  • Continued culvert work to continue between Barber Farm Road and the Jericho/Richmond town line.
  • Structure rehabilitation and sidewalk work to continue between VT 289 ramps and Tiffany Lane.
  • Shoulder / ditch work will continue between Sand Hill Road and VT 289.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!