VT 117 – September 25, 2018

Written by on September 24, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • 9:00am Weather permitting, paving to continue from Sand Hill Road westbound to VT-289.
  • 7:00am  Continued structure rehab work around the VT-289 area.
  • 7:00am  Continued culvert work around the Jericho/Richmond town line.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.
 
DRIVE SLOW – USE CAUTION!

Subscribe

If you enjoyed this article, subscribe now to receive more just like it.

Subscribe via RSS Feed

Comments are closed.

Top