VT Route 2A

Written by on September 20, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, September 24, 2018:

Monday thru Wednesday:

  • Continued work on the installation of the pedestrian crosswalk at Bittersweet Circle to include the installation of the flashing beacon signals.

 Wednesday thru Friday:

  • Installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic during this work.

 Motorists should expect minimal delays and use caution while traveling thru the work zone.