The following is the anticipated work schedule for the week beginning Monday, October 01, 2018:

 Monday thru Friday:

  • Final work on the installation of the pedestrian crosswalk at Bittersweet Circle to include pavement markings.

 Monday thru Wednesday:

  • Installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.

 Motorists should expect minimal delays and use caution while traveling thru the work zone.